Foressa Mountain Town Construction Updates Q2 2023
Site Development
The land development of Phase 1A is now 100% complete, while Phase 1B has reached 84% progress, with a target completion set for Q4 2023.
Amenities
The Main Pavilion is currently at 91% completion, with the structure’s target completion set for Q3 2023.
The Phase 1A Streetscape and main entry signage is ongoing and is anticipated to be finished by Q4 2023.
Work on the Outdoor Camping Grounds is scheduled to begin with a target completion in Q4 2023.
The Phase 1A Pocket Parks and Outdoor Events Area are projected to be completed by Q1 2024.
Turnover
83 lots have been turned over to vecinos in Phase 1A.
Value Appreciation
Residential lot investments at Foressa Mountain Town are enjoying 92% value appreciation.
Priced at Php 7,300 per sqm during its launch year in 2017, a residential lot in this community is now at Php 14,000 per sqm.
Sales
The available inventory consists of 4 units in Phase 1A and 34 units in Phase 1B, offering stretched promo terms.
Know someone who is looking for a mountain sanctuary? Be one of our Referral Partners and earn up to Php 50,000* for every successful referral. http://bit.ly/vecinoreferral
Reserve our special Hillside Lots now to get a P729K discount on regular terms and as much as P2.9M for cash payments.
Talk to your Property Specialist or Broker today.
Terms and conditions apply.