Foressa Mountain Town Construction Updates Q3 2023
Site Development
The land development of Phase 1A is now 100% complete, while Phase 1B has reached 96% progress, with a target completion set for Q4 2023.
Amenities
The Main Pavilion is at 91% completion, with the target for structure completion set for Q4 2023.
The Phase 1A Streetscape and main entry signage are currently in progress and are slated for completion by Q4 2023.
Phase 1A Pocket Parks and the Outdoor Events Area are scheduled for completion in Q2 2024.
Turnover
87 lots have been turned over to vecinos in Phase 1A.
Value Appreciation
Residential lot investments at Foressa Mountain Town are enjoying 92% value appreciation.
Priced at Php 7,300 per sqm during its launch year in 2017, a residential lot in this community is now at Php 14,000 per sqm.
Sales
The available inventory consists of 12 units in Phase 1A and 29 units in Phase 1B.
Remaining units for Phase 1A are ready for occupancy, with special discounts available.
Know someone who is looking for a mountain sanctuary?
Be one of our Referral Partners and earn up to Php 50,000* for every successful referral.
Reserve our special Hillside Lots now to get a P729K discount on regular terms and as much as P2.9M for cash payments.
Talk to your Property Specialist or Broker today.
Terms and conditions apply.