Foressa Mountain Town Construction Updates Q3 2024

SITE DEVELOPMENT

Phase Light 1A site development is 96% complete, targeting completion in Q1 2025, while Phase Light 1B is 80% complete, with a target completion in Q2 2025.

Site Development covers site clearing, grading, roads, utilities, open parking, and related work.

 

AMENITIES

The Main Pavilion is fully completed and operationally ready. The Outdoor Events Area is set for completion by Q1 2025, with Diamond Park to follow in Q3, and the Phase Light 1A Pocket Park Trees in Q4 2025.

Amenities include the completion of the clubhouse, pools, function areas, parks, playgrounds, courts, guardhouses, landscaped spaces, and equipment rentals.

 

VECINO TURNOVERS

114 lots have been turned over to vecinos in Phase Light 1A.
Vecino Turnovers are residential lots that have been turned over to vecinos.

 

VALUE APPRECIATION

Residential lot investments at Foressa Mountain Town are enjoying 99% value appreciation. Priced at Php 7,300 per sqm during its launch year in 2017, a residential lot in this community is now at Php 14,500 per sqm.
Value Appreciation indicates the increase in property value since the launch year.

 

SALES

The available inventory consists of 9 units in Phase Light 1A and 25 units in Phase Light 1B.
Sales represent the available inventory for the quarter.

Know someone who is looking for a mountain sanctuary? Be one of our Referral Partners and earn up to Php 50,000* for every successful referral.

http://bit.ly/vecinoreferral.

Talk to your Property Specialist or Broker today.

 

Aboitiz Land and Asmara Group to Bring Eco-Luxury to Foressa

Aboitiz Land, in partnership with the Asmara Group, will soon open a new bar and restaurant in Foressa Mountain Town. This collaboration will bring eco-luxury dining to the serene mountains, offering a refreshing escape from the hustle and bustle of the metro.

Read More

This heralds a series of activations for Foressa, so interested business owners are invited to partner with us.  For inquiries, please email us at aboitizland@aboitiz.com.

Terms and conditions apply.

The general updates from Aboitiz Land are intended for informational purposes only and are subject to change without prior notice. For individual unit status, refer to the Vecino App or contact our Customer Service team at aboitizland.customer.service@aboitiz.com.

Foressa Mountain Town Construction Updates Q3 2023

Site Development

The land development of Phase 1A is now 100% complete, while Phase 1B has reached 96% progress, with a target completion set for Q4 2023.

 

Amenities

The Main Pavilion is at 91% completion, with the target for structure completion set for Q4 2023.

The Phase 1A Streetscape and main entry signage are currently in progress and are slated for completion by Q4 2023.

Phase 1A Pocket Parks and the Outdoor Events Area are scheduled for completion in Q2 2024.

 

Turnover

87 lots have been turned over to vecinos in Phase 1A.

 

Value Appreciation

Residential lot investments at Foressa Mountain Town are enjoying 92% value appreciation.

Priced at Php 7,300 per sqm during its launch year in 2017, a residential lot in this community is now at Php 14,000 per sqm.

 

Sales

The available inventory consists of 12 units in Phase 1A and 29 units in Phase 1B.

Remaining units for Phase 1A are ready for occupancy, with special discounts available.

 

Know someone who is looking for a mountain sanctuary?

Be one of our Referral Partners and earn up to Php 50,000* for every successful referral.

http://bit.ly/vecinoreferral

Reserve our special Hillside Lots now to get a P729K discount on regular terms and as much as P2.9M for cash payments.

Talk to your Property Specialist or Broker today.

Terms and conditions apply.